A property owner in the city or a person expressly authorized in writing by the owner may file an application for a Planned Development for the area of land for which the Planned Development is requested. Here’s how it works:

Press enter or click to view image in full size

Step 1 Complete the Neighborhood Participation Program.

Get Natalie K. Mitchell’s stories in your inbox

Join Medium for free to get updates from this writer.

Step 3 Submit application to the City Planning Commission.

Step 4 CPC will hold a hearing within 50 days after the application is docketed.

Step 5 CPC will issue a recommendation to the City Council within 60 days of the opening of the hearing.

Step 6 City Council will hold a hearing and take action within 60 days of receiving the CPC recommendation.

Step 7 If the City Council approves the application, the Law Department will be directed to draft an ordinance. The ordinance must lay over 21 days after it is introduced by the City Council.

--

--